I need to make a diagram for completion-review-revision-approval process of technical drawings. The diagram needs to show both the process milestones (completion-review-revision-approval) and also their schedule distributed on weeks.
However I cannot imagine graphically how can I show both the milestones and the schedule.
For example, there are 3 drawings lets say:
Drawing A will be - completed between Week 1-3 - reviewed between Week 3-4 - revision between Week 4-5 - Approved on Week 6
Drawing B will be
- completed between Week 1-4
- reviewed between Week 4-5
- revision between Week 5-6
- Approved on Week 7
Drawing C will be
- completed between Week 3-5
- viewed between Week 5-6
- revision between Week 6-7
- Approved on Week 8
As you can understand, the milestone dates of drawings are distributed into the weeks and intersecting with each other. For example, while the revision of Drawing B is going on, Drawing A is already approved.
Normally we show these process with Gantt chart but I am looking for alternative cool ideas.
I hope explanation of my question is clear to you.
Thanks.